                                             SURE CHANGE Version 1.1
                                             ©1996 Terry W. Towle
                                             1-864-967-4606 or 1-500-OR DELAY
     
 
Software Registered To: Terry W. Towle
                        HST Software
     
Comparison between projects BLD1 and BLD2
Report Title: Test with application.processmessages
Comparison Run Completed: 7/28/96 at 4:50:07 PM
Durations (OD, RD, TF & Lag) are in HOURS.
     
 
The number of activities in the Target Schedule is: 86
The number of activities in the Update Schedule is: 87
     
Section 1 - These activities have been deleted from update.
     
Act ID     Description                                      TF    OD
---------- ------------------------------------------------ ----- -----
   NO ACTIVITY DELETIONS BY UPDATE
     
Section 2 - These activities have been added to update.
     
Act ID     Description                                      TF    OD
---------- ------------------------------------------------ ----- -----
ZZ999      Added Scope for Change Order #1                      0   160
     
Section 3 - These percents have been changed by update.
     
Act ID     Description                                      Old %  New %  Change
---------- ------------------------------------------------ ------ ------ ------
BA450      Assemble Brick Samples                             50.0   60.0   10.0
BA63       Foundation/Site Work                               14.9   11.5   -3.4
BA39       Office Building Addition                            5.5    4.7    -.8
BA42       Brick                                               4.3    5.2     .9
     
Section 4 - These original durations have been changed by update.
     
Act ID     Description                                      Old OD New OD Change
---------- ------------------------------------------------ ------ ------ ------
BA407      Prepare and Solicit Bids for Flooring                40     32     -8
BA408      Review Bids for Flooring                             24     32      8
BA530      Review and Approve Brick Samples                     80     88      8
BA39       Office Building Addition                           2072   2152     80
BA41       HVAC                                               1576   1656     80
BA89       Interior                                            352    432     80
BA90       Plumbing and Lighting Fixtures                      112   1552   1440
     
Section 5 - These remaining durations have been changed by update.
     
Act ID     Description                                      Old RD New RD Change
---------- ------------------------------------------------ ------ ------ ------
BA407      Prepare and Solicit Bids for Flooring                40     32     -8
BA408      Review Bids for Flooring                             24     32      8
BA450      Assemble Brick Samples                               40     32     -8
BA530      Review and Approve Brick Samples                     80     88      8
BA39       Office Building Addition                           1696   1776     80
BA41       HVAC                                               1576   1656     80
BA89       Interior                                            352    432     80
BA90       Plumbing and Lighting Fixtures                      112   1552   1440
     
Section 6 - These early starts have been changed by update.
     
Act ID     Description                                      Old ES           New ES           TF   
---------- ------------------------------------------------ ---------------- ---------------- -----
BA408      Review Bids for Flooring                         28Oct94 08:00 am 27Oct94 08:00 am   872
BA530      Review and Approve Brick Samples                 30Sep94 08:00 am 29Sep94 08:00 am   232
BA912      Install Plumbing Fixtures                        06Jul95 08:00 am 23Sep94 08:00 am    24
BA930      Paint Building Interior                          26May95 08:00 am 06Jul95 08:00 am   144
BA940      Touch-up and Clean-up                            13Jul95 08:00 am 27Jul95 08:00 am     0
BA941      Test and Balance HVAC Equipment                  14Jul95 08:00 am 28Jul95 08:00 am     0
BA950      Finishes Milestone                               17Jul95 08:00 am 31Jul95 08:00 am     0
BA960      Punch List                                       17Jul95 08:00 am 31Jul95 08:00 am     0
BA970      Building Addition Complete                       19Jul95 08:00 am 02Aug95 08:00 am     0
BA90       Plumbing and Lighting Fixtures                   19Jun95 08:00 am 23Sep94 08:00 am    24
BA93       Painting                                         26May95 08:00 am 06Jul95 08:00 am   144
     
Section 7 - These early finishes have been changed by update.
     
Act ID     Description                                      Old EF           New EF           TF   
---------- ------------------------------------------------ ---------------- ---------------- -----
BA407      Prepare and Solicit Bids for Flooring            27Oct94 05:00 pm 26Oct94 05:00 pm   872
BA450      Assemble Brick Samples                           29Sep94 05:00 pm 28Sep94 05:00 pm   232
BA912      Install Plumbing Fixtures                        07Jul95 05:00 pm 26Sep94 05:00 pm    24
BA930      Paint Building Interior                          15Jun95 05:00 pm 26Jul95 05:00 pm   144
BA940      Touch-up and Clean-up                            13Jul95 05:00 pm 27Jul95 05:00 pm     0
BA941      Test and Balance HVAC Equipment                  14Jul95 05:00 pm 28Jul95 05:00 pm     0
BA950      Finishes Milestone                               14Jul95 05:00 pm 28Jul95 05:00 pm     0
BA960      Punch List                                       18Jul95 05:00 pm 01Aug95 05:00 pm     0
BA970      Building Addition Complete                       18Jul95 05:00 pm 01Aug95 05:00 pm     0
BA39       Office Building Addition                         18Jul95 05:00 pm 01Aug95 05:00 pm     0
BA41       HVAC                                             14Jul95 05:00 pm 28Jul95 05:00 pm     0
BA89       Interior                                         18Jul95 05:00 pm 01Aug95 05:00 pm     0
BA90       Plumbing and Lighting Fixtures                   07Jul95 05:00 pm 21Jun95 05:00 pm    24
BA93       Painting                                         15Jun95 05:00 pm 26Jul95 05:00 pm   144
     
Section 8 - These actual starts have been changed by update.
     
Act ID     Description                                      Old AS           New AS  
---------- ------------------------------------------------ ---------------- ----------------
BA480      Assemble and Submit Flooring Samples                              23Sep94 08:00 am
BA38       Floor and Carpeting                                               23Sep94 08:00 am
     
Section 9 - These actual finishes have been changed by update.
     
Act ID     Description                                      Old AF           New AF  
---------- ------------------------------------------------ ---------------- ----------------
   NO ACTUAL FINISHES CHANGED BY UPDATE
     
Section 10 - These total floats have been changed by update.
     
Act ID     Description                                      Old TF New TF Change
---------- ------------------------------------------------ ------ ------ ------
BA912      Install Plumbing Fixtures                            24   1728   1704
BA913      Install Elevator Cab and Finishes                   304    384     80
BA930      Paint Building Interior                             144      0   -144
BA86       Elevator                                            304    384     80
BA90       Plumbing and Lighting Fixtures                       24    192    168
BA93       Painting                                            144      0   -144
     
Section 11 - These calendars have been changed by update.
     
Act ID     Description                                      Old Cal New Cal TF   
---------- ------------------------------------------------ ------- ------- -----
   NO CALENDAR CHANGES BY UPDATE
     
Section 12 - These descriptions have been changed by update.
     
Act ID     Old Description                                  New Description
---------- ------------------------------------------------ ------------------------------------------------
BA800      Building Enclosed                                Building Semi-Enclosed
     
 
The number of relationships in the Target Schedule is: 87
The number of relationships in the Update Schedule is: 86
     
Section 13 - These relationships have been deleted by update.
     
Pred ID    Description
     Succ ID    Description                                      Link Lag 
--------------- ------------------------------------------------ ---- ----
BA910      Install Floor and Carpeting                      
     BA912      Install Plumbing Fixtures                          FS    0
BA911      Finish Carpentry and Millwork                    
     BA940      Touch-up and Clean-up                              FS    0
     
Section 14 - These relationships have been added by update.
     
Pred ID    Description
     Succ ID    Description                                      Link Lag 
--------------- ------------------------------------------------ ---- ----
BA911      Finish Carpentry and Millwork                    
     BA930      Paint Building Interior                            SS    0
     
Section 15 - These relationship lags have been changed by update.
     
Pred ID    Description
     Succ ID    Description                                      Link Old Lag New Lag
--------------- ------------------------------------------------ ---- ------- -------
   NO RELATIONSHIP LAGS CHANGED BY UPDATE
     
Section 16 - These relationship driving links have been changed by update.
     
Pred ID    Description
     Succ ID    Description                                      Link Lag DLink Status 
--------------- ------------------------------------------------ ---- --- -------------
BA890      Drywall in Offices                               
    BA930      Paint Building Interior                             SS  56  Was Driving
BA930      Paint Building Interior                          
    BA940      Touch-up and Clean-up                               FS   0  Now Driving