** NOTE: Items have been manually deleted from this sample report
for size considerations SURE CHANGE Version 1.1
©1996 Terry W. Towle
1-864-967-4606 or 1-500-OR DELAY
Software Registered To: Terry W. Towle
HST Software
Comparison between projects BLD1 and BLD2
Report Title: Test with application.processmessages
Comparison Run Completed: 7/28/96 at 4:50:07 PM
Durations (OD, RD, TF & Lag) are in HOURS.
The number of activities in the Target Schedule is: 86
The number of activities in the Update Schedule is: 87
Section 1 - These activities have been deleted from update.
Act ID Description TF OD
---------- ------------------------------------------------ ----- -----
NO ACTIVITY DELETIONS BY UPDATE
Section 2 - These activities have been added to update.
Act ID Description TF OD
---------- ------------------------------------------------ ----- -----
ZZ999 Added Scope for Change Order #1 0 160
Section 3 - These percents have been changed by update.
Act ID Description Old % New % Change
---------- ------------------------------------------------ ------ ------ ------
BA450 Assemble Brick Samples 50.0 60.0 10.0
BA63 Foundation/Site Work 14.9 11.5 -3.4
BA39 Office Building Addition 5.5 4.7 -.8
BA42 Brick 4.3 5.2 .9
Section 4 - These original durations have been changed by update.
Act ID Description Old OD New OD Change
---------- ------------------------------------------------ ------ ------ ------
BA407 Prepare and Solicit Bids for Flooring 40 32 -8
BA408 Review Bids for Flooring 24 32 8
BA530 Review and Approve Brick Samples 80 88 8
BA39 Office Building Addition 2072 2152 80
BA41 HVAC 1576 1656 80
BA89 Interior 352 432 80
BA90 Plumbing and Lighting Fixtures 112 1552 1440
Section 5 - These remaining durations have been changed by update.
Act ID Description Old RD New RD Change
---------- ------------------------------------------------ ------ ------ ------
BA407 Prepare and Solicit Bids for Flooring 40 32 -8
BA408 Review Bids for Flooring 24 32 8
BA450 Assemble Brick Samples 40 32 -8
BA530 Review and Approve Brick Samples 80 88 8
BA39 Office Building Addition 1696 1776 80
BA41 HVAC 1576 1656 80
BA89 Interior 352 432 80
BA90 Plumbing and Lighting Fixtures 112 1552 1440
Section 6 - These early starts have been changed by update.
Act ID Description Old ES New ES TF
---------- ------------------------------------------------ ---------------- ---------------- -----
BA408 Review Bids for Flooring 28Oct94 08:00 am 27Oct94 08:00 am 872
BA530 Review and Approve Brick Samples 30Sep94 08:00 am 29Sep94 08:00 am 232
BA912 Install Plumbing Fixtures 06Jul95 08:00 am 23Sep94 08:00 am 24
BA930 Paint Building Interior 26May95 08:00 am 06Jul95 08:00 am 144
BA940 Touch-up and Clean-up 13Jul95 08:00 am 27Jul95 08:00 am 0
BA941 Test and Balance HVAC Equipment 14Jul95 08:00 am 28Jul95 08:00 am 0
BA950 Finishes Milestone 17Jul95 08:00 am 31Jul95 08:00 am 0
BA960 Punch List 17Jul95 08:00 am 31Jul95 08:00 am 0
BA970 Building Addition Complete 19Jul95 08:00 am 02Aug95 08:00 am 0
BA90 Plumbing and Lighting Fixtures 19Jun95 08:00 am 23Sep94 08:00 am 24
BA93 Painting 26May95 08:00 am 06Jul95 08:00 am 144
Section 7 - These early finishes have been changed by update.
Act ID Description Old EF New EF TF
---------- ------------------------------------------------ ---------------- ---------------- -----
BA407 Prepare and Solicit Bids for Flooring 27Oct94 05:00 pm 26Oct94 05:00 pm 872
BA450 Assemble Brick Samples 29Sep94 05:00 pm 28Sep94 05:00 pm 232
BA912 Install Plumbing Fixtures 07Jul95 05:00 pm 26Sep94 05:00 pm 24
BA930 Paint Building Interior 15Jun95 05:00 pm 26Jul95 05:00 pm 144
BA940 Touch-up and Clean-up 13Jul95 05:00 pm 27Jul95 05:00 pm 0
BA941 Test and Balance HVAC Equipment 14Jul95 05:00 pm 28Jul95 05:00 pm 0
BA950 Finishes Milestone 14Jul95 05:00 pm 28Jul95 05:00 pm 0
BA960 Punch List 18Jul95 05:00 pm 01Aug95 05:00 pm 0
BA970 Building Addition Complete 18Jul95 05:00 pm 01Aug95 05:00 pm 0
BA39 Office Building Addition 18Jul95 05:00 pm 01Aug95 05:00 pm 0
BA41 HVAC 14Jul95 05:00 pm 28Jul95 05:00 pm 0
BA89 Interior 18Jul95 05:00 pm 01Aug95 05:00 pm 0
BA90 Plumbing and Lighting Fixtures 07Jul95 05:00 pm 21Jun95 05:00 pm 24
BA93 Painting 15Jun95 05:00 pm 26Jul95 05:00 pm 144
Section 8 - These actual starts have been changed by update.
Act ID Description Old AS New AS
---------- ------------------------------------------------ ---------------- ----------------
BA480 Assemble and Submit Flooring Samples 23Sep94 08:00 am
BA38 Floor and Carpeting 23Sep94 08:00 am
Section 9 - These actual finishes have been changed by update.
Act ID Description Old AF New AF
---------- ------------------------------------------------ ---------------- ----------------
NO ACTUAL FINISHES CHANGED BY UPDATE
Section 10 - These total floats have been changed by update.
Act ID Description Old TF New TF Change
---------- ------------------------------------------------ ------ ------ ------
BA912 Install Plumbing Fixtures 24 1728 1704
BA913 Install Elevator Cab and Finishes 304 384 80
BA930 Paint Building Interior 144 0 -144
BA86 Elevator 304 384 80
BA90 Plumbing and Lighting Fixtures 24 192 168
BA93 Painting 144 0 -144
Section 11 - These calendars have been changed by update.
Act ID Description Old Cal New Cal TF
---------- ------------------------------------------------ ------- ------- -----
NO CALENDAR CHANGES BY UPDATE
Section 12 - These descriptions have been changed by update.
Act ID Old Description New Description
---------- ------------------------------------------------ ------------------------------------------------
BA800 Building Enclosed Building Semi-Enclosed
The number of relationships in the Target Schedule is: 87
The number of relationships in the Update Schedule is: 86
Section 13 - These relationships have been deleted by update.
Pred ID Description
Succ ID Description Link Lag
--------------- ------------------------------------------------ ---- ----
BA910 Install Floor and Carpeting
BA912 Install Plumbing Fixtures FS 0
BA911 Finish Carpentry and Millwork
BA940 Touch-up and Clean-up FS 0
Section 14 - These relationships have been added by update.
Pred ID Description
Succ ID Description Link Lag
--------------- ------------------------------------------------ ---- ----
BA911 Finish Carpentry and Millwork
BA930 Paint Building Interior SS 0
Section 15 - These relationship lags have been changed by update.
Pred ID Description
Succ ID Description Link Old Lag New Lag
--------------- ------------------------------------------------ ---- ------- -------
NO RELATIONSHIP LAGS CHANGED BY UPDATE
Section 16 - These relationship driving links have been changed by update.
Pred ID Description
Succ ID Description Link Lag DLink Status
--------------- ------------------------------------------------ ---- --- -------------
BA890 Drywall in Offices
BA930 Paint Building Interior SS 56 Was Driving
BA930 Paint Building Interior
BA940 Touch-up and Clean-up FS 0 Now Driving
|